The Antaris 12 kW installed in Baden-Württemberg

Here is another installation of the Antaris 12 kW on a 24 m mast in BW. The scope of the permit includes a soil survey, the tested mast statics and the bat control. The Antaris 12 kW works in 3-phase parallel to the grid with heating support and thus supplies a farm with electricity and […]

And it goes on in Bavaria…

Here, the Antaris 5.5 kW with the repeller diameter D4.40 m is installed on a 15m high tipping mast in Bavaria. https://braun-windturbinen.com/…/antari…/antaris-5-5-kw The Antaris works in 3 phases parallel to the TRIO 5.8. Safety: PLC wind, V DC monitoring, helicopter function, Generator CK7.5 kW If you have any questions about the project, please contact us, […]

The ANTARIS 12 kW in Serbia

Here the Antaris 12 kW was installed on an 18m high lattice mast. The wind turbine works in 3-phase parallel to the grid with the PVS 10 from FIMER: https://braun-windturbinen.com/produkte/wind-wechselrichter/ The installation was carried out by the guys from: https://telefon-inzenjering.co.rs/ .Thank you and respect for performance! The usual safety parameters for the Antaris 12 are […]

The Antaris 12 kW in Schleswig-Holstein!

Here, both Antaris 12 kW wind turbines are now working on 18m masts in the immediate vicinity. In the wind turbine currently installed, the Smart!wind+ was installed with the TRIO 10 kW from SMA. The rear one still works with the Smart!wind. Both wind turbines operate in 3-phase parallel to the grid. The usual safety […]

ANTARIS wind turbines, built to meet the highest demands!

The ANTARIS 12 kW is installed here on a 12m tilting mast, procedure-free in Lower Saxony. https://braun-windturbinen.com/…/antaris…/antaris-12-kw The wind turbine works in 3-phase parallel to the PVS 10 kW from FIMER, here is the link: https://www.fimer.com/…/dreiphasige…/pvs-1012515-tl The usual safety parameters for the Antaris 12 are as follows: PLC wind, V DC monitoring, helicopter function. In […]

Let’s continue with the installations – this time in NL

Here the Antaris 5.5 kW with the repeller D4.40m https://braun-windturbinen.com/…/antari…/antaris-5-5-kw The wind turbine is installed on a 12m high lattice mast. The mast can be tilted on site and via the jut tree. The Antaris 5.5 works in 3-phase parallel to the TRIO 5.5. The Antaris serves as a student project here: https://www.hanze.nl/de The installation […]

Funding for small wind turbines by the Federal Ministry

Federal Ministry of Food and Agriculture also supports small wind turbines in the field of agriculture and horticulture! Take advantage of the opportunity of 40% funding until 30.06.2021. If you have any questions about the project, please call here! https://braun-windturbinen.com/kontakt/ Joy of the wind with ANTARIS wind turbines.   Directive-Funding-Energy-Efficiency-2020-1  

ANTARIS wind turbine meets New Energy trade fair in Husum

This year, the ANATARIS wind turbine was once again a magnet for trade fair visitors.An unexpectedly large number of interested parties came to the trade fair stand for technical discussions.Most of them were already familiar with the facility and were able to convince themselves of the quality “Made in Gemany” on site.Overall, we draw a […]

The next ANTARIS 4.5 kW for clean electricity and heat

The 4.5 kW system works in 3-phase parallel to the grid with a set base load of 2.0 kW for the household electricity consumption.If the system produces more energy than the set grid capacity, it is transferred to a 6.0 kW heating element for domestic water heating .Thus, the customer has almost 100% self-consumption, even […]

ANTARIS small wind turbines – free wind power for house and yard

Below are the yield overviews from 11.2015 of 2 ANTARIS turbines with 6.5 kW and 9.5 kW nominal power each.In the case of the 9.5 system, the yields from Energy Net (blue, house network) and Energy Chopper (red, heating element) must be added.The yields from the 2nd heating element are not visible, but amount to […]