With a lot of dedication, enthusiasm and an eye for detail, the installation of the Francis turbine has now been successfully completed.
Respect for the successful work and expertise!
https://de.wikipedia.org/wiki/Francis-Turbine
On the electrical side, the CK7.5 generator (7.5kW) was installed as an energy supplier.
This works with approx. 600rpm @ 5.0 kW in continuous operation.
https://braun-windturbinen.com/produkte/generatoren/
The 3-phase TRIO 5.8 takes over the grid-parallel operation as a grid inverter.
The inverter works with an adjustable characteristic curve via controller, which is installed in the control cabinet.
In addition, a 6.0 kW brake resistor is installed.
Online monitoring runs via 24/7 Mini PC.
If you have any questions about the project, please contact us, we will be happy to advise you!